Scope of Work
Upgrades at the Agawam Compressor Station. Phase one consisted of all electrical and light mechanical for a new auxiliary building. This included:
- Site lighting
- Gear installation
- Cable tray installation
- Lightning protection
- Interior lighting
- Wiring
- Installation of a new MCC
- Demo and rebuild of an existing control building MCC
- ESD interlock system work, that consisted of supply and installation of electrical and insulated tubing to automate ten manual valves
- Installation of new battery backup system in the auxiliary building
Phase two* work included:
- Demo of electrical to an old compressor in compressor building D
- New wiring installation
- Gear installation
- Cable tray installation
- Lighting installation
- Electrical work for a new solar compressor in compressor building D
*due to the Covid-19 pandemic, this project was split into two phases
Industry
Oil & Gas
Client
Kinder Morgan
Location
Agawam, MA
Manhours
6,545
Duration
15 months